Question 1
During framing, a homeowner asks the lead carpenter to add a window to the new family room. The carpenter estimates the change will take about two hours and roughly $600 in materials. What is the project manager's CORRECT first action?
Show answer & explanation
Correct answer: D - Issue a written change order and obtain the client's signature before work proceeds